How to Make a Gantt Chart: Step-by-Step Guide (With Example)
November 22, 2026
Plan Smarter. Execute Faster.
Manage projects on web and mobile. One subscription for your whole team.
A Gantt chart turns a list of tasks into a picture of time. Each task becomes a bar on a calendar, bars are linked where one piece of work depends on another, and anyone can see what happens this week, what is waiting, and when the project should finish. It answers the question every stakeholder asks: "When will it be done, and what has to happen first?"
This guide shows how to make a Gantt chart step by step, with a worked example (a small clinic treatment room renovation) you can copy, a quick comparison with lists and kanban boards, and the mistakes that make charts unreliable. It is written for project managers, construction and field teams, healthcare operations leads, and small business owners.
What is a Gantt chart?
A Gantt chart is a horizontal bar chart of a project schedule. Tasks run down the left side, dates run across the top, and each bar starts on the task's start date and ends on its finish date. Lines or arrows between bars show dependencies, so you can see which tasks have to wait for others.
The parts of a Gantt chart
- Task list. The work items, usually grouped into phases, with subtasks under larger tasks.
- Timeline. The date scale across the top, shown in days, weeks, or months depending on the length of the project.
- Bars. One per task. The length of the bar is the duration.
- Dependencies. Links that set the order of work, most often Finish-to-Start (B starts after A finishes), Start-to-Start, and Finish-to-Finish.
- Checkpoints. Short tasks that mark a key moment, such as a sign-off or a handover. (See our guide to project milestones.)
- Owners and status. Who is responsible for each bar and whether it is on track, done, or late.
Before you start: what you need
For a small project, a first chart takes about an hour if these inputs are ready:
- A one-sentence goal with a target date, for example "Room 4 back in use as a treatment room by 12 March".
- A rough list of the work, ideally from a work breakdown structure.
- Fixed dates you cannot move: deliveries, inspections, events, contract dates, staff availability.
- The people or teams who will do the work, so each task gets an owner.
How to make a Gantt chart in 8 steps
1. Break the project into phases and tasks
Start with three to six phases (for example: prepare, strip out, services, finishes, handover), then list the tasks inside each. A good task is something one person or team can finish and someone else can check. "Do electrics" is too vague; "Electrical first fix for new sockets and exam light" is a task. Keep tasks between half a day and two weeks, and split longer ones into subtasks.
2. Estimate durations
Estimate each task in working days and include review time, drying time, and waiting for answers. Ask the person who will do the work. If a supplier quotes a lead time, put that wait on the chart as its own task, because waiting often decides the finish date.
3. Link tasks with dependencies
For each task, ask: "What has to happen before this can start, or before it can finish?" Then link the tasks:
- Finish-to-Start (FS): painting starts after wall repairs finish. This is the most common link.
- Start-to-Start (SS): waste removal starts when strip-out starts, and both run together.
- Finish-to-Finish (FF): the final clean cannot finish until equipment testing finishes.
Only link tasks that are truly connected. Our guide to FS, SS and FF dependencies covers them with construction examples.
4. Set start dates and let the chain place the rest
Give the first tasks a start date and anchor anything tied to a fixed date. Each dependent task then starts when its predecessor allows, and the last bar shows the realistic finish date. If it is later than your goal, you found out before any work began.
5. Add checkpoint tasks
Add a short task for each moment that matters to stakeholders, such as "Layout signed off" or "Handover to clinic", and link it to the work that must be done first so it moves when that work moves.
6. Assign an owner to every task
One name (or one team) per bar. If one electrician has three overlapping bars in the same week, the chart is not realistic yet, so re-sequence the work.
7. Review the draft with the people doing the work
Walk the chart with the team for fifteen minutes. People spot missing tasks ("who removes the old sink?"), wrong durations, and hidden links. For the chain of tasks that sets the finish date, see the critical path method.
8. Track progress and update every week
Once a week, mark finished tasks, update dates that moved, and check the effect on the finish date and the next checkpoint. A chart untouched for a month is no longer a plan.
Worked example: clinic treatment room renovation
This is an illustrative example, not a real project. A small clinic wants to convert a storage room into a treatment room with new cabinets, a sink, an exam chair, and updated lighting. Durations are in working days, with Day 1 as the first working day of the project.
| # | Task | Duration | Depends on | Planned days |
|---|---|---|---|---|
| 1 | Agree layout and finishes with clinic manager | 2 days | None (start) | Day 1 to 2 |
| 2 | Order cabinets, sink and exam chair | 1 day | 1 (FS) | Day 3 |
| 3 | Supplier lead time (delivery) | 10 days | 2 (FS) | Day 4 to 13 |
| 4 | Protect corridor and strip out old shelving | 2 days | 1 (FS) | Day 3 to 4 |
| 5 | Waste removal | 2 days | 4 (SS) | Day 3 to 4 |
| 6 | Electrical and plumbing first fix | 3 days | 4 (FS) | Day 5 to 7 |
| 7 | Wall repairs and painting | 3 days | 6 (FS) | Day 8 to 10 |
| 8 | Flooring | 2 days | 7 (FS) | Day 11 to 12 |
| 9 | Install cabinets and sink | 2 days | 8 (FS) and 3 (FS) | Day 14 to 15 |
| 10 | Install exam chair and lighting, test equipment | 2 days | 9 (FS) | Day 16 to 17 |
| 11 | Final clean | 2 days | 10 (FF) | Day 16 to 17 |
| 12 | Handover to clinic (checkpoint task) | 1 day | 11 (FS) | Day 18 |
What the chart tells you
- The finish date is Day 18, about three and a half working weeks. That is the date to share with the clinic, not a guess.
- The delivery wait drives the end of the project. Flooring is done on Day 12, but cabinets cannot go in until the delivery arrives after Day 13. If the supplier slips by three days, handover slips by three days. Ordering on Day 3 instead of after painting is what keeps the project short.
- The SS and FF links save time safely. Waste removal runs alongside strip-out, and the final clean overlaps testing but cannot be signed off until testing is done.
Natural checkpoint tasks here are "Layout signed off" after task 1 and the handover at the end. To share it as a timeline, see how to create a project timeline.
Gantt chart vs. task list vs. kanban board
| View | Best for | Shows dates and order? |
|---|---|---|
| Task list | Capturing work and daily to-dos | Dates yes, order between tasks not really |
| Kanban board | Flowing work with few hard dates, such as support requests | Status yes, timing and order mostly no |
| Gantt chart | Projects with a deadline, handoffs between people, and work that must happen in sequence | Yes, both, plus the effect of a delay |
Most teams use both: the Gantt chart holds the plan, and a daily list keeps each person focused on today.
Common Gantt chart mistakes
- Too much detail. Hundreds of tiny tasks make a chart nobody updates.
- Missing waiting time. Deliveries, approvals, and drying times belong on the chart as tasks.
- Dates typed in by hand instead of linked. Unlinked bars stay put when a task moves, and the chart quietly becomes wrong.
- Linking everything to everything. Link only real constraints.
- No owners. A bar without a name is a task nobody feels responsible for.
- Never updating it. The value comes from the weekly update, not the first draft.
Making a Gantt chart in GanttMaster
GanttMaster is a project management app for the web, iPhone and iPad, made by our team. Here is how the steps above map onto it:
- Create the project and add tasks. Add tasks and subtasks with start and end dates, a priority, and an assigned user or team. That covers steps 1, 2 and 6.
- Link tasks. Open a task, go to the Dependencies tab, choose Add Dependency, pick Finish-to-Start, Start-to-Start, or Finish-to-Finish, and use Select Task to choose the linked task. Checkpoint tasks such as "Handover to clinic" are short tasks linked the same way.
- See the chart. The Gantt view draws each task as a bar across the dates, with connector lines showing the dependencies, so you can review the sequence with your team (step 7).
- Keep it moving day to day. The Today view lists project tasks due today alongside personal tasks with reminders, which makes the weekly update (step 8) much lighter. Risk and budget tracking sit in the same project, so the schedule, the risks, and the money stay together.
There is no per-user pricing, so trades, clinic staff, or part-time helpers can update their own tasks without counting seats. You can start with a 1-week free trial, then $5.99 a month or $34.99 a year.
Start with the next project on your desk
Making a Gantt chart is honest thinking written down: list the work, estimate it, link what depends on what, give every bar an owner, and update it weekly. Swap your own tasks into the clinic example and you will have a first chart, and a realistic finish date, today.
Plan it on the web or on your iPhone and iPad
Full disclosure: we make GanttMaster, a project management app for the web, iPhone and iPad with FS/SS/FF dependencies, tasks and subtasks, checkpoint tasks, a Today view with reminders, team assignment, risk and budget tracking, and no per-user pricing. Start with a 1-week free trial on the web or in the app, then $5.99/month or $34.99/year.